Project update
Solar on a site that never switches off
April 2026 · Equator Solar engineering team · 3 min read
/Next Media Park (NBS).webp)
Next Media Park is the home of NBS and Uganda’s largest independent media house. Broadcast continues through a grid fault, and a site that goes dark on air loses its audience. The reliability requirement is therefore closer to a hospital than to an office.
A round-the-clock load with a daytime peak
The load runs continuously, with a heavy daytime component on top of the round-the-clock base. We sized the system, 86 kWp of PV with 96 kWh of storage, to cover the daytime peak. It does not carry the whole site.
Carrying a 24-hour broadcast load entirely on solar and batteries would need a much larger battery, used mostly to cover the quiet hours. Covering the daytime peak puts the budget where most of the consumption is.
Built to be extended
A finance partner paid for the system, and it has since been expanded. We design for that from the start. Space in the switchgear, the cable routes and the roof layout costs little at build time and a lot to add later.
Why it is a reference we point to
On a broadcast site the public notices every interruption. A system that holds up there also meets the requirements of sites with lower demands.
The project
Next Media Park (NBS)
86 kWp PV + 96 kWh battery · Kampala, Uganda · 2026
All project references →Solar for Institutions and Development →More from the Knowledge Hub
Project update
Seven years, three systems, and a CT scanner at Naggalama
A hospital relationship that started with 12 kWp in 2019 now carries a CT scanner through outages. Each of the three systems solved a different problem.
Technology brief
Why we specify LFP over NMC on weak grids
A battery on a weak Ugandan grid cycles more often than the same battery in a stable market. That decides the chemistry we choose and how long it lasts.
Project update
What full daytime cover actually looks like at a food processor
A 250 kWp grid-tied system at Sumz Food Industries in Nkoowe covers the full daytime process load and is paid for under a power purchase agreement (PPA). The sizing follows from the load and from Uganda’s grid rules.
Technology brief
Zero feed-in: what it means when the grid will not take your surplus
Uganda has no net metering for commercial and industrial users. This fact decides how we size every grid-tied system.