Project update
Solar on a site that never switches off
April 2026 · Equator Solar engineering team · 3 min read
/Next Media Park (NBS).webp)
Next Media Park is the home of NBS and Uganda’s largest independent media house. Broadcast does not pause for a grid fault, and a site that goes dark on air is a site that has lost its audience, so the reliability requirement here is closer to a hospital than to an office.
A round-the-clock load with a daytime peak
The load runs continuously, with a heavy daytime component on top of the round-the-clock base. We sized the system, 86 kWp of PV with 96 kWh of storage, to shave that daytime peak, which means taking the top off the heaviest demand, rather than to carry the whole site.
Carrying a 24-hour broadcast load entirely on solar and batteries would have meant a much larger battery, used mostly to cover the quiet hours. Shaving the peak puts the money where the consumption actually is.
Built to be extended
The system was financed through a finance partner and has since been expanded, which is worth designing for from the start. Leaving room in the switchgear, the cable routes and the roof layout costs little at build time and a lot to add later.
Why it is a reference we point to
Broadcast infrastructure is unforgiving in a way that suits how we work. If a system holds up on a site where the public sees every interruption, it will hold up on sites with gentler requirements.
The project
Next Media Park (NBS)
86 kWp PV + 96 kWh battery · Kampala, Uganda · 2026
All project references →Solar for Institutions and Development →More from the Knowledge Hub
Project update
Seven years, three systems, and a CT scanner at Naggalama
A hospital relationship that started with 12 kWp in 2019 now carries a CT scanner through grid interruptions. Here is what changed at each step, and why.
Technology brief
Why we specify LFP over NMC on weak grids
A battery on a weak Ugandan grid works harder than the same battery in a stable market. Chemistry choice follows from that, and so does service life.
Project update
What full daytime cover actually looks like at a food processor
A 250 kWp grid-tied system at Sumz Food Industries in Nkoowe covers the full daytime process load and was delivered under a PPA. Here is why the sizing worked out the way it did.
Technology brief
Zero feed-in: what it means when the grid will not take your surplus
Uganda has no net metering for commercial and industrial users. That single fact shapes how every grid-tied system on this site gets sized.