Project update
Seven years, three systems, and a CT scanner at Naggalama
June 2026 · Equator Solar engineering team · 4 min read

Most of our long-running client relationships began with a modest system that worked. The system then grew as the site grew. Naggalama Hospital is the clearest example we have.
2019: twelve kilowatts and a clinical daytime load
The first system was a 12 kWp grid-tied installation in captive-power configuration, which means it supplied only the hospital’s own use. We sized it for the daytime clinical load. There was no storage, because at that point the hospital wanted to bring down its power bill. The project was delivered together with Partnerschaft Gesunde Welt e.V., the German partner that has stayed involved at Naggalama ever since.
A modest system gives everybody, us included, real operating data from the actual site instead of assumptions.
2021: backup enters the picture
Two years of that data made the next question clear. The savings were working, but the critical wards still lost power whenever the grid dropped. The extension added PV capacity to reach 22 kWp and a 21 kWh supercapacitor backup for the critical wards.
We chose supercapacitor storage because supercapacitors store energy electrically rather than chemically. They handle frequent short interruptions well and wear less from that kind of duty than a battery does.
2026: a CT scanner changes the requirement
A CT scanner is a different kind of load. Its peak draw is high and arrives suddenly. An interruption during imaging spoils the scan while the patient is already on the table. The system has to respond faster than any person could.
The system we built for it is 50 kWp of PV with a 100 kWh battery, sized for the scanner circuit rather than the whole hospital. It carries the scanner through interruptions on its own. When an outage runs long, it hands over to the generator in a controlled way, so the scanner keeps running during the switch.
What we take from it
The same site needed three different answers in seven years. The first system was about cost. The second kept the critical wards running. The third protects a single piece of equipment that the hospital has built a service around. Sizing a system correctly starts with knowing which question the site is asking.
The project
Naggalama Hospital CT Scan
50 kWp PV + 100 kWh battery · Naggalama, Uganda · 2026
All project references →Solar for Hospitals and Clinics →More from the Knowledge Hub
Technology brief
Why we specify LFP over NMC on weak grids
A battery on a weak Ugandan grid cycles more often than the same battery in a stable market. That decides the chemistry we choose and how long it lasts.
Project update
What full daytime cover actually looks like at a food processor
A 250 kWp grid-tied system at Sumz Food Industries in Nkoowe covers the full daytime process load and is paid for under a power purchase agreement (PPA). The sizing follows from the load and from Uganda’s grid rules.
Project update
Solar on a site that never switches off
Next Media Park in Kampala has 86 kWp of PV and 96 kWh of storage. Broadcast runs 24 hours a day, which changes what a solar system has to be.
Technology brief
Zero feed-in: what it means when the grid will not take your surplus
Uganda has no net metering for commercial and industrial users. This fact decides how we size every grid-tied system.